Due to international developments, St. Maarten General Hospital (SMGH) construction activities have slowed down over the recent weeks.As a lingering result of the pandemic, there have been delays in purchasing and shipping materials and steep increases in the prices of construction materials. These challenges make it unrealistic to build the hospital at the original price and by the original due date. SMMC and the contractor (FINSO) are working on a solution to address the increased cost of mate...